| Year | Street | From | To | Scope | Contract |
| FY14 | Albany Street | Portland St | Mass Ave | Paving, Sidewalk, Ped Ramps | Reconstruction by Massachusetts Institute of Technology |
| FY15 | Alpine Street | Vassal Ln | Bay State Rd | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 9 |
| FY14 | Amory St | Hampshire St | Broadway | Paving, Sidewalk, Ped Ramps | Street Reconstruction Contract 17 |
| FY14 | Appleton Rd | Appleton | Cul De Sac | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 8b |
| FY14 | Appleton St | Highland Ave | Concord Ave | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 8b |
| FY15 | Bay State Rd | New St | Alpine St | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 9 |
| FY13 | Bent St | First St | Second St | Paving, Sidewalk, Ped Ramps | Private Developer |
| FY14 | Binney St | Third St | First St | Paving, Sidewalk, Ped Ramps | Alexandria Development |
| FY17 | Binney St | Gallileo Way | Third St | Paving, Ped Ramps | Street Reconstruction Contract FY17 |
| FY15 | Birch St | Concord Ave | Bay State Rd | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 9 |
| FY15 | Bishop Allen Dr | Columbia St | Douglas St | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM017 Contract II Bishop Allen Drive |
| FY15 | Blackstone St | | | Paving, Sidewalk, Ped Ramps | Street Reconstruction Contract |
| FY14 | Blakeslee St | Huron Ave | Reservoir | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 8b |
| FY13 | Boardman St | Broadway | Harvard St | Paving, Sidewalk, Ped Ramps | Broadway Contract |
| FY14 | Broadway | Ames St | Third St | Paving, Sidewalk, Ped Ramps | Reconstruction by Massachusetts Highway Department |
| FY13 | Broadway | Prospect St | Windsor St | Paving, Sidewalk, Ped Ramps | Broadway Contract |
| FY13 | Broadway | Portland St | Windsor St | Paving, Sidewalk, Ped Ramps | Broadway Contract |
| FY14 | Cambridge Common | | | Multi-Use Bicycle / Pedestrian Path | Reconstruction by Massachusetts Highway Department |
| FY13 | Cambridge St Tunnel | Quincy St | Mass Ave | Paving, Sidewalk, Ped Ramps | Cambridge Street Tunnel Contract |
| FY13 | Charles St | First St | Second St | Paving, Sidewalk, Ped Ramps | Private Developer |
| FY13 | Chauncy St | Mass Ave | Garden St | Paving, Ped Ramps | Street Reconstruction Contract 13 |
| FY14 | Chilton St | Huron Ave | Vassal Ln | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 8b |
| FY15 | Chilton St | Vassal Ln | Field St | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 9 |
| FY15 | Concord Ave | Huron Ave | Fresh Pond Pkwy | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 9 |
| FY15 | Copley St | Walden St | Fayerweather St | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 9 |
| FY15 | Corporal Burns Rd | Concord Ave | Bay State Rd | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 9 |
| FY13 | Davis St | Harvard St | Broadway | Paving, Sidewalk, Ped Ramps | Street Reconstruction Contract 14 |
| FY14 | Decatur St | Brookline St | Pearl St | Sewer Separation, Paving, Ped Ramps | Common Manhole Removal Contract 7 |
| FY18 | Dodge St | Western Ave | Callender St | Paving, Sidewalk, Ped Ramps | Street Reconstruction Contract FY18 |
| FY14 | Douglas St | Mass Ave | Bishop Allen Dr | Paving, Sidewalk, Ped Ramps | Street Reconstruction Contract 16 |
| FY14 | Douglas St | Bishop Allen Dr | Mass Ave | Sewer Separation, Paving, Ped Ramps | Sewer Separation Contract CAM017 Contract II Bishop Allen Drive |
| FY14 | Dunstable Rd | Appleton | Cul De Sac | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 8b |
| FY14 | Emily St | Brookline St | Sidney St | Sewer Separation, Paving, Ped Ramps | Common Manhole Removal Contract 7 |
| FY13 | Fawcett St | Concord Ave | Mooney St | Paving, Sidewalk, Ped Ramps | Fawcett Street |
| FY14 | Fayerweather St | Reservoir St | Vassal Ln | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 8b |
| FY15 | Fayerweather St | Vassal Ln | Field St | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 9 |
| FY15 | Fayerweather St | Walden St | Hazel St | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 9 |
| FY15 | Fern St | Concord Ave | Bay State Rd | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 9 |
| FY15 | Field St | Fayerweather St | Alpine St | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 9 |
| FY15 | Field St | Birch St | Alpine St | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 9 |
| FY13 | Forest St | Mass Ave | Somerville Line | Sewer Separation, Paving, Sidewalks, Ped Ramps | Sewer Separation Phase 6 Contract 3F Frost Street |
| FY14 | Franklin St | Pleasant St | Western Ave | Paving, Sidewalk, Ped Ramps | Western Avenue Reconstruction Contract |
| FY14 | Frost St | Roseland St | Forest St | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Phase 6 Contract 3F Frost Street |
| FY13 | Frost St | Forest St | Prentiss St | Sewer Separation, Paving, Sidewalks, Ped Ramps | Sewer Separation Phase 6 Contract 3F Frost Street |
| FY14 | Fulkerson | Cambridge St | Charles | Paving, Sidewalk, Ped Ramps | Street Reconstruction Contract 17 |
| FY15 | Garden St | Walden St | Field St | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 9 |
| FY15 | Granville Rd | Vassal Ln | Saville St | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 9 |
| FY14 | Granville Rd | Huron Ave | Vassal Ln | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 8b |
| FY14 | Green St | Pleasant St | Western Ave | Paving, Sidewalk, Ped Ramps | Western Avenue Reconstruction Contract |
| FY13 | Grozier Rd | Fresh Pond Pkwy | Cul De Sac | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 8a |
| FY14 | Gurney St | Fayerweather St | Huron Ave | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 8b |
| FY13 | Hawthorne Park | Lexington Ave | Cul De Sac | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 8a |
| FY15 | Hayes St | Howard St | Dead End | Paving, Sidewalk, Ped Ramps | Street Reconstruction Contract FY15 |
| FY15 | Hazel St | Field St | Garden St | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 9 |
| FY17 | Hilliard St | Brattle St | Mt Auburn St | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Harvard Square Phase IV |
| FY13 | Hovey Ave | Magnolia Ave | Cambridge St | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Phase VI Contract 3E Myrtle Magnolia |
| FY15 | Hurlbut St | Linnean St | Martin St | Paving, Sidewalk, Ped Ramps | Street Reconstruction Contract FY15 |
| FY16 | Huron Ave | Raymond St | Concord Ave | Paving, Sidewalk, Ped Ramps | Street Reconstruction Contract FY16 |
| FY14 | Huron Ave | Fresh Pond Pkwy | Lakeview Ave | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 8b |
| FY14 | Huron Ave | Lakeview Ave | Concord Ave | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 8b |
| FY14 | Hutchinson St | Reservoir St | Appleton St | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 8b |
| FY13 | Irving St | Kirkland St | Scott St | Paving, Sidewalk, Ped Ramps | Street Reconstruction Contract 15 |
| FY15 | Ivy St | Fayerweather St | Garden St | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 9 |
| FY17 | Jay St | River St | Kinnaird St | Paving, Sidewalk, Ped Ramps | Street Reconstruction Contract FY17 |
| FY15 | Kinnaird St | Putnam Ave | Bend Beyond Hancock St | Paving, Sidewalk, Ped Ramps | Street Reconstruction Contract FY15 |
| FY16 | Kinnaird St | River St | Bend Beyond Hancock St | Paving, Sidewalk, Ped Ramps | Street Reconstruction Contract FY16 |
| FY13 | Lakeview Ave | Worthington St | Brattle St | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 8a |
| FY13 | Larch Rd | Fresh Pond | Fresh Pond | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 8a |
| FY13 | Lexington Ave | Fresh Pond | Brattle St | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 8a |
| FY13 | Linnaean St | Mass Ave | Raymond St | Paving, Ped Ramps | Street Reconstruction Contract 14 |
| FY13 | Locke St | Meacham Rd | Somerville | Paving, Sidewalk, Ped Ramps | Street Reconstruction Contract 15 |
| FY13 | Longfellow Rd | Mt. Auburn St | End | Paving, Sidewalk, Ped Ramps | Street Reconstruction Contract 15 |
| FY13 | Lopez St | Spring St | Park Ave | Paving, Sidewalk, Ped Ramps | Street Reconstruction Contract 14 |
| FY13 | Magnolia St | Roberts Rd | Line St | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Phase VI Contract 3E Myrtle Magnolia |
| FY14 | Main St | Wadsworth St | Ames St | Paving, Sidewalk, Ped Ramps | Main Street |
| FY14 | Main St | Broad Canal Way | Longfellow Bridge | Sewer Separation, Paving, Ped Ramps | Common Manhole Removal Contract 7 |
| FY13 | Malcolm Rd | Lakeview Ave | Standish St | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 8a |
| FY14 | Mason St | Garden St | Brattle St | Paving, Sidewalk, Ped Ramps | Street Reconstruction Contract 16 |
| FY14 | Mass Ave | Beech St | Russell St | Paving, Sidewalk, Ped Ramps | Street Reconstruction Contract 16 |
| FY14 | Mass Ave | Everett St | Linnaean St | Paving, Ped Ramps | Street Reconstruction Contract 16 |
| FY14 | Mass Ave | Sellers St | Pleasant St | Sidewalk, Ped Ramps South Side Only | H2 / C2 2013 |
| FY14 | Mass Ave | Pleasant St | Temple St | Sidewalk, Ped Ramps South Side Only | H2 / C2 2013 |
| FY14 | Mass Ave | Norfolk St | Douglas St | Sidewalk, Ped Ramps North Side Only | H2 / C2 2013 |
| FY13 | Meacham Rd | Mass Ave | Somerville | Paving, Sidewalk, Ped Ramps | Street Reconstruction Contract 15 |
| FY14 | Mead St | Cogswell Ave | Walden St | Paving, Sidewalk, Ped Ramps | Street Reconstruction Contract 17 |
| FY13 | Moore St | Harvard Ave | Broadway | Paving, Sidewalk, Ped Ramps | Street Reconstruction Contract 14 |
| FY13 | Mt Auburn St | Gibson St | Fresh Pond Pkwy | Paving, Sidewalk, Ped Ramps | Street Reconstruction Contract 15 |
| FY16 | Mt Auburn St | Mass Ave | Holyoke St | Paving, Sidewalk, Ped Ramps | Street Reconstruction Contract FY16 |
| FY14 | Mt. Auburn St | JFK | Holyoke St | Paving, Sidewalk, Ped Ramps | H2 / C2 2013 |
| FY13 | Myrtle Av | Kirkland St | Magnolia Ave | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Phase VI Contract 3E Myrtle Magnolia |
| FY16 | Newport Rd | Mass Ave | Forrest St | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Phase 6 Contract 3F Frost Street |
| FY13 | Oxford St | Beacon St | Garfield St | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Phase 6 Contract 3F Frost Street |
| FY17 | Pearl St | Granite St | Erie St | Paving, Sidewalk, Ped Ramps | Street Reconstruction Contract FY17 |
| FY16 | Pearl St | Erie St | Mass Ave | Paving, Sidewalk, Ped Ramps | Street Reconstruction Contract FY16 |
| FY14 | Pleasant St | Franklin St | Western Ave | Paving, Sidewalk, Ped Ramps | Western Avenue Reconstruction Contract |
| FY13 | Putnam Ave | Pleasant St | Mass Ave | Paving | NStar Electic |
| FY14 | Reservoir St | Highland Ave | Vassal Ln | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 8b |
| FY18 | River St | Memorial Dr | Franklin St | Paving, Sidewalk, Ped Ramps | Street Reconstruction Contract FY18 |
| FY14 | Riverside Place | Western Ave | Cul-de-sac | Paving, Sidewalk, Ped Ramps | Western Avenue Reconstruction Contract |
| FY16 | Roseland St | Mass Ave | Somerville Line | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Phase 6 Contract 3F Frost Street |
| FY14 | Royal Ave | Huron Ave | Concord Ave | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 8b |
| FY14 | Saville St | Reservoir St | Appleton St | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 8b |
| FY15 | Saville St | Reservoir St | Fayerweather St | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 9 |
| FY13 | Scott St | Irving St | Bryant St | Paving, Sidewalk, Ped Ramps | Street Reconstruction Contract 15 |
| FY14 | Second St | Rogers St | Charles St | Paving, Ped Ramps | Street Reconstruction Contract 16 |
| FY14 | Second St | Hurley St | Gore St | Paving, Ped Ramps | Street Reconstruction Contract 16 |
| FY13 | Second St | Bent St | Charles St | Paving, Sidewalk, Ped Ramps | Private Developer |
| FY13 | Shea Rd | Mass Ave | Somerville | Paving, Sidewalk, Ped Ramps | Street Reconstruction Contract 15 |
| FY14 | Sherman St | Garden St | Walden St | Paving, Sidewalk, Ped Ramps | Street Reconstruction Contract 17 |
| FY18 | Sixth St | Cambridge St | Charles | Paving, Sidewalk, Ped Ramps | Street Reconstruction Contract FY18 |
| FY13 | Smith Pl | Fawcett St | Mooney St | Paving, Sidewalk, Ped Ramps | Fawcett Street |
| FY15 | Smith Place | Concord Ave | Mooney St | Paving, Sidewalk, Ped Ramps | Street Reconstruction Contract FY15 |
| FY15 | Soden St | Western Ave | Franklin St | Paving, Sidewalk, Ped Ramps | Western Avenue Reconstruction Contract |
| FY13 | Spring St | Fulkerson St | Third St | Paving, Sidewalk, Ped Ramps | Street Reconstruction Contract 14 |
| FY13 | Spring St | Third St | First St | Paving, Sidewalk, Ped Ramps | Street Reconstruction Contract 14 |
| FY13 | Standish St | Vassal Ln | Huron Ave | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 8a |
| FY14 | Temple St | Mass Ave | Bishop Allen Dr | Paving, Sidewalk, Ped Ramps | Street Reconstruction Contract 16 |
| FY15 | Thorndike St | Dead End Beyond Fulkerson | Scriappa St | Paving, Sidewalk, Ped Ramps | Street Reconstruction Contract FY15 |
| FY14 | Tudor St | Brookline St | Sidney St | Sewer Separation, Paving, Ped Ramps | Common Manhole Removal Contract 7 |
| FY14 | Tufts St | Magazine St | Pearl St | Paving, Sidewalk, Ped Ramps | Street Reconstruction Contract 16 |
| FY13 | Upton St | Pleasant St | Magazine St | Sidewalk | Miscellaneous Sidewalk Contract |
| FY14 | Valentine St | Brookline St | Pearl St | Sewer Separation, Paving, Ped Ramps | Common Manhole Removal Contract 7 |
| FY13 | Vassal Lane | Lakeview Ave | Standish St | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 8a |
| FY14 | Vassal Lane | Standish St | Huron Ave | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 8b |
| FY14 | Walden St | Vassal Ln | Concord Ave | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 8b |
| FY15 | Walden St | Concord Ave | Garden St | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 9 |
| FY16 | Walden St | Sherman | Garden St | Paving, Sidewalk, Ped Ramps | Street Reconstruction Contract FY17 |
| FY13 | Waterhouse St | Mass Ave | Garden St | Paving, Sidewalk, Ped Ramps | Street Reconstruction Contract 15 |
| FY13 | Waterman Rd | Standish St | Cul De Sac | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 8a |
| FY14 | Waverly Street Path | Erie | Mirriam | Paving, Sidewalk, Ped Ramps | Main Street |
| FY13 | Western Ave | Green St | Memorial Dr | Sewer Separation, Paving, Sidewalk, Ped Ramps | Western Avenue Reconstruction Contract |
| FY13 | Woodbridge St | Mass Ave | Somerville | Paving, Sidewalk, Ped Ramps | Street Reconstruction Contract 15 |
| FY14 | Wyman Rd | Sparks St | Cul De Sac | Sewer Separation, Paving, Sidewalk, Ped Ramps | Sewer Separation Contract CAM2/4 8b |