Five Year Street and Sidewalk Reconstruction Plan
  Below is a list of streets and sidewalks that are scheduled for reconstruction between FY2013 and FY2018. To learn more about the City' s approach to prioritizing street and sidewalk reconstruction please see the full five year street and sidewalk plan (pdf).

 
YearStreetFromToScopeContract
FY15Albany StreetMass AveOsborn StPaving, Sidewalk, Ped RampsNovartis
FY14Albany Street Portland StMass AvePaving, Sidewalk, Ped RampsReconstruction by Massachusetts Institute of Technology
FY16Alpine StreetVassal LnBay State RdSewer Separation, Paving, Sidewalk, Ped RampsConcord Avenue Sewer Separation Contract
FY16Ames StBroadwayMain StPaving, Sidewalks, Ped RampsBoston Properties
FY15Amory StHampshire StBroadwayPaving, Sidewalk, Ped RampsStreet Reconstruction Contract 17
FY16Appleton RdAppleton Cul De SacSewer Separation, Paving, Sidewalk, Ped RampsHuron B Sewer Separation Contract
FY16Appleton StBrattle StConcord AveSewer Separation, Paving, Sidewalk, Ped RampsHuron B Sewer Separation Contract
FY16Bay State RdNew StAlpine StSewer Separation, Paving, Sidewalk, Ped RampsConcord Avenue Sewer Separation Contract
FY14Bent StFirst StSecond StPaving, Sidewalk, Ped RampsPrivate Developer
FY14Binney StThird StFirst StPaving, Sidewalk, Ped RampsAlexandria Development
FY18Binney StGallileo WayThird StPaving, Ped RampsStreet Reconstruction Contract FY18
FY16Birch StConcord AveBay State RdSewer Separation, Paving, Sidewalk, Ped RampsConcord Avenue Sewer Separation Contract
FY17Bishop Allen DrColumbia StDouglas StSewer Separation, Paving, Sidewalk, Ped RampsBishop Allen DrivSewer Separation Contract CAM017 Contract II
FY16Blakeslee StHuron AveReservoirSewer Separation, Paving, Sidewalk, Ped RampsHuron B Sewer Separation Contract
FY13Boardman StBroadwayHarvard StPaving, Sidewalk, Ped RampsBroadway Contract
FY17Brattle StPalmer StBrattle St Harvard Square 2017
FY13BroadwayPortland StWindsor StPaving, Sidewalk, Ped RampsBroadway Contract
FY14BroadwayAmes StThird StPaving, Sidewalk, Ped RampsReconstruction by Massachusetts Highway Department
FY13BroadwayProspect StWindsor StPaving, Sidewalk, Ped RampsBroadway Contract
FY16Cambridge Common  Multi-Use Bicycle / Pedestrian PathReconstruction by Massachusetts Highway Department of Transportation
FY14Cambridge St TunnelQuincy StMass AvePaving, Sidewalk, Ped RampsCambridge Street Tunnel Contract
FY17Channing StMt AuburnBrattle StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract FY17
FY13Chauncy StMass AveGarden StPaving, Ped RampsStreet Reconstruction Contract 13
FY16Cherry StMain StHarvard StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract FY16
FY16Chilton StHuron AveVassal LnSewer Separation, Paving, Sidewalk, Ped RampsHuron B Sewer Separation Contract
FY16Chilton StVassal LnField StSewer Separation, Paving, Sidewalk, Ped RampsConcord Avenue Sewer Separation Contract
FY16Concord AveHuron AveFresh Pond PkwySewer Separation, Paving, Sidewalk, Ped RampsConcord Avenue Sewer Separation Contract
FY16Concord LaneFresh Pond PkwyEndSewer Separation, Paving, Sidewalk, Ped RampsNew Street / Concord Lane
FY16Copley StWalden StFayerweather StSewer Separation, Paving, Sidewalk, Ped RampsConcord Avenue Sewer Separation Contract
FY16Corporal Burns RdConcord AveBay State RdSewer Separation, Paving, Sidewalk, Ped RampsConcord Avenue Sewer Separation Contract
FY18Cottage StMagazine StPearl StSewer Separation, Paving, Sidewalk, Ped RampsCambridgeport Sewer Separation Lopez / Cottage
FY17Davenport StMass AveElm St NPaving, Sidewalk, Ped RampsStreet Reconstruction Contract FY17
FY13Davis StHarvard StBroadwayPaving, Sidewalk, Ped RampsStreet Reconstruction Contract 14
FY14Decatur StBrookline StPearl StSewer Separation, Paving, Ped RampsCommon Manhole Removal Contract 7
FY13Douglas StBishop Allen DrMass AveSewer Separation, Paving, Ped RampsBishop Allen DrivSewer Separation Contract CAM017 Contract II
FY15Douglas StMass AveBishop Allen DrPaving, Sidewalk, Ped RampsMiscellaneous Sidewalk Contract
FY16Dudley StMass AveClifton StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract FY16
FY16Dunstable RdAppleton Cul De SacSewer Separation, Paving, Sidewalk, Ped RampsHuron B Sewer Separation Contract
FY17Eliot StBrattle StJFK StPaving, Sidewalk, Ped RampsHarvard Square 2017
FY14Emily StBrookline StSidney StSewer Separation, Paving, Ped RampsCommon Manhole Removal Contract 7
FY14Fawcett StConcord AveMooney StPaving, Sidewalk, Ped RampsFawcett Street
FY16Fayerweather StBrattle StVassal LnSewer Separation, Paving, Sidewalk, Ped RampsHuron B Sewer Separation Contract
FY16Fayerweather StWalden StHazel StSewer Separation, Paving, Sidewalk, Ped RampsConcord Avenue Sewer Separation Contract
FY16Fayerweather StVassal LnField StSewer Separation, Paving, Sidewalk, Ped RampsConcord Avenue Sewer Separation Contract
FY16Fern StConcord AveBay State RdSewer Separation, Paving, Sidewalk, Ped RampsConcord Avenue Sewer Separation Contract
FY16Field StFayerweather StAlpine StSewer Separation, Paving, Sidewalk, Ped RampsConcord Avenue Sewer Separation Contract
FY16Field StBirch StAlpine StSewer Separation, Paving, Sidewalk, Ped RampsConcord Avenue Sewer Separation Contract
FY13Forest StMass AveSomerville LineSewer Separation, Paving, Sidewalks, Ped RampsFrost Street Sewer Separation Phase 6 Contract 3F
FY14Franklin StPleasant StWestern AvePaving, Sidewalk, Ped RampsWestern Avenue Reconstruction Contract 2
FY17Franklin StPleasantStLandsdowne StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract FY17
FY13Frost StForest StPrentiss StSewer Separation, Paving, Sidewalks, Ped RampsFrost Street Sewer Separation Phase 6 Contract 3F
FY14Frost StRoseland StForest StSewer Separation, Paving, Sidewalk, Ped RampsFrost Street Sewer Separation Phase 6 Contract 3F
FY15FulkersonCambridge StCharlesPaving, Sidewalk, Ped RampsStreet Reconstruction Contract 17
FY14Garden StHuron AveWalden StPaving, Ped RampsNStar Electric
FY14Garden StHuron AveWaterhouse StPaving, Ped RampsNStar Electric
FY16Garden StWalden StField StSewer Separation, Paving, Sidewalk, Ped RampsConcord Avenue Sewer Separation Contract
FY16Granville RdVassal LnSaville StSewer Separation, Paving, Sidewalk, Ped RampsConcord Avenue Sewer Separation Contract
FY16Granville RdHuron AveVassal LnSewer Separation, Paving, Sidewalk, Ped RampsHuron B Sewer Separation Contract
FY14Green StPleasant StWestern AvePaving, Sidewalk, Ped RampsWestern Avenue Reconstruction Contract
FY15Grozier RdFresh Pond PkwyCul De SacSewer Separation, Paving, Sidewalk, Ped RampsHuron A Sewer Separation Contract
FY16Gurney StFayerweather StHuron AveSewer Separation, Paving, Sidewalk, Ped RampsHuron B Sewer Separation Contract
FY16Harding StSouthCambridge StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract FY16
FY15Hawthorne ParkLexington AveCul De SacSewer Separation, Paving, Sidewalk, Ped RampsHuron A Sewer Separation Contract
FY16Hayes StHoward StEndPaving, Sidewalk, Ped RampsStreet Reconstruction Contract FY16
FY15Hayes StHoward StDead EndPaving, Sidewalk, Ped RampsStreet Reconstruction Contract 18
FY16Hazel StField StGarden StSewer Separation, Paving, Sidewalk, Ped RampsConcord Avenue Sewer Separation Contract
FY16Healey StParker StBuckingham StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract FY16
FY13Hovey AveMagnolia AveCambridge StSewer Separation, Paving, Sidewalk, Ped RampsMyrtle Magnolia Sewer Separation Phase VI Contract 3E
FY16Hudson StMass AveHudson PlPaving, Sidewalk, Ped RampsStreet Reconstruction Contract FY16
FY16Hurlbut StLinnean StMartin StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract 18
FY18Huron AveRaymond StConcord AvePaving, Sidewalk, Ped RampsStreet Reconstruction Contract FY18
FY16Huron AveFresh Pond PkwyLakeview AveSewer Separation, Paving, Sidewalk, Ped RampsHuron B Sewer Separation Contract
FY16Huron AveLakeview AveConcord AveSewer Separation, Paving, Sidewalk, Ped RampsHuron B Sewer Separation Contract
FY16Hutchinson StReservoir StAppleton StSewer Separation, Paving, Sidewalk, Ped RampsHuron B Sewer Separation Contract
FY14Irving StKirkland StScott StPaving, Sidewalk, Ped RampsMiscellaneous Sidewalk Contract
FY16Ivy StFayerweather StGarden StSewer Separation, Paving, Sidewalk, Ped RampsConcord Avenue Sewer Separation Contract
FY18Jay StRiver StKinnaird StPaving, Sidewalk, Ped RampsWestern Avenue Reconstruction Contract 2
FY16Kenwood StPutnam AvePrince StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract FY16
FY15Kinnaird StPutnam AveHancock StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract 18
FY18Kinnaird StRiver StHancock StPaving, Sidewalk, Ped RampsWestern Avenue Reconstruction Contract 2
FY17Kirkland StOxford StSomerville LineSewer Separation, Paving, Sidewalk, Ped RampsSewer Separation Agassiz -- Kirkland
FY15Lakeview AveWorthington StBrattle StSewer Separation, Paving, Sidewalk, Ped RampsHuron A Sewer Separation Contract
FY15Larch RdFresh PondFresh PondSewer Separation, Paving, Sidewalk, Ped RampsHuron A Sewer Separation Contract
FY16Lawn StOxford StCushing StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract FY16
FY15Lexington AveFresh PondBrattle StSewer Separation, Paving, Sidewalk, Ped RampsHuron A Sewer Separation Contract
FY13Linnaean StMass AveRaymond StPaving, Ped RampsStreet Reconstruction Contract 14
FY13Locke StMeacham RdSomervillePaving, Sidewalk, Ped RampsStreet Reconstruction Contract 15
FY16Longfellow BridgeBostonThird StPavings, Sidewalks, RampsMassDOT
FY15Longfellow RdMt. Auburn StEndPaving, Sidewalk, Ped RampsStreet Reconstruction Contract 17
FY18Lopez AveBrookline StPearl StSewer Separation, Paving, Sidewalk, Ped RampsCambridgeport Sewer Separation Lopez / Cottage
FY13Lopez StSpring StPark AvePaving, Sidewalk, Ped RampsStreet Reconstruction Contract 14
FY13Magnolia StRoberts RdLine StSewer Separation, Paving, Sidewalk, Ped RampsMyrtle Magnolia Sewer Separation Phase VI Contract 3E
FY15Main StBroad Canal Way Longfellow BridgeSewer Separation, Paving, Ped RampsCommon Manhole Removal Contract 7
FY15Main StWadsworth StAmes StPaving, Sidewalk, Ped RampsMain Street
FY15Malcolm RdLakeview AveStandish StSewer Separation, Paving, Sidewalk, Ped RampsHuron A Sewer Separation Contract
FY16Martin StMass AveBowdoin StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract FY16
FY15Mason StGarden StBrattle StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract 16
FY15Mass AveBeech StRussell StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract 16
FY16Mass AveLinnaean StSomerville AvePaving, Ped RampsStreet Reconstruction Contract FY15B
FY14Mass AveHarvard StMt Auburn StPaving, Ped RampsNStar Electric
FY15Mass AveEverett StLinnaean StPaving, Ped RampsStreet Reconstruction Contract 16
FY16Mass AveSellers StPleasant StSidewalk, Ped Ramps South Side OnlyHarvard Sq / Central Sq 2014
FY16Mass AvePleasant StTemple StSidewalk, Ped Ramps South Side OnlyHarvard Sq / Central Sq 2014
FY16Mass AveNorfolk StDouglas StSidewalk, Ped Ramps North Side OnlyHarvard Sq / Central Sq 2014
FY13Meacham RdMass AveSomervillePaving, Sidewalk, Ped RampsStreet Reconstruction Contract 15
FY15Mead StCogswell AveWalden StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract 17
FY14Moore StHarvard StBroadwayPaving, Sidewalk, Ped RampsStreet Reconstruction Contract 14
FY15Mt Auburn StGibson StFresh Pond PkwyPaving, Sidewalk, Ped RampsStreet Reconstruction Contract 17
FY15Mt. Auburn StJFKHolyoke StPaving, Sidewalk, Ped RampsHarvard Sq 2014
FY16Muller AveChurchill AveMurray Hill RdPaving, Sidewalk, Ped RampsStreet Reconstruction Contract FY15B
FY14Murray Hill RdFresh Pond PkwyChurchill AveSewer Separation, Paving, Sidewalk, Ped RampsCommon Manhole Removal Contract 7
FY13Myrtle AvKirkland StMagnolia AveSewer Separation, Paving, Sidewalk, Ped RampsMyrtle Magnolia Sewer Separation Phase VI Contract 3E
FY16New StConcord AveEndPaving, Sidewalk, Ped RampsNew Street / Concord Lane
FY16Newport RdMass AveForrest StSewer Separation, Paving, Sidewalk, Ped RampsFrost Street Sewer Separation Phase 6 Contract 3F
FY14Norris StMass AveCedar StPavingPrivate Developer / Misc. Patch
FY15Osborn StMass AveMain StPaving, Sidewalk, Ped RampsNovartis
FY13Oxford StBeacon StGarfield StSewer Separation, Paving, Sidewalk, Ped RampsFrost Street Sewer Separation Phase 6 Contract 3F
FY18Park AveHuron AveHolworthy StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract FY18
FY16Parker stBuckingham StConcord AvePaving, Sidewalk, Ped RampsStreet Reconstruction Contract FY16
FY17Pearl StGranite StErie StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract FY17
FY16Pearl StErie StMass AvePaving, Sidewalk, Ped RampsStreet Reconstruction Contract FY16
FY14Pleasant StRiver StreetWestern AvePaving, Sidewalk, Ped RampsWestern Avenue Reconstruction Contract
FY15Pleasant StFairmont St Paving, Ped RampsStreet Reconstruction Contract 17
FY16Porter StHarding StWarren StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract FY16
FY16Putnam AveMagee StKinnaird StPaving, Ped RampsStreet Reconstruction Contract FY16
FY13Putnam AvePleasant StMass AvePavingNStar Electic
FY14Quincy StCambridge StHarvard RdPaving, Ped RampsNStar Electric
FY16Reservoir StHighland AveVassal LnSewer Separation, Paving, Sidewalk, Ped RampsHuron B Sewer Separation Contract
FY16Richard AveMass AveMuller AvePaving, Sidewalk, Ped RampsStreet Reconstruction Contract FY15B
FY14Riverside PlaceWestern AveCul-de-sacPaving, Sidewalk, Ped RampsWestern Avenue Reconstruction Contract
FY17Roberts RdKirkland StCambridge StSewer Separation, Paving, Sidewalk, Ped RampsSewer Separation Agassiz -- Kirkland
FY14Rogers StThird stSecond StPaving, Sidewalks, RampsAlexandria Development
FY16Roseland StMass AveSomerville LineSewer Separation, Paving, Sidewalk, Ped RampsFrost Street Sewer Separation Phase 6 Contract 3F
FY16Royal AveHuron AveConcord AveSewer Separation, Paving, Sidewalk, Ped RampsHuron B Sewer Separation Contract
FY16Saville StReservoir StAppleton StSewer Separation, Paving, Sidewalk, Ped RampsHuron B Sewer Separation Contract
FY16Saville StReservoir StFayerweather StSewer Separation, Paving, Sidewalk, Ped RampsConcord Avenue Sewer Separation Contract
FY16School StBishop Allen DrWindsor StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract FY16
FY14Scott StIrving StBryant StPaving, Sidewalk, Ped RampsMiscellaneous Sidewalk Contract
FY15Second StRogers StCharles StPaving, Ped RampsStreet Reconstruction Contract 16
FY15Second StHurley StGore StPaving, Ped RampsStreet Reconstruction Contract 16
FY14Second StBent StCharles StPaving, Sidewalk, Ped RampsPrivate Developer
FY13Shea RdMass AveSomervillePaving, Sidewalk, Ped RampsStreet Reconstruction Contract 15
FY15Sherman StGarden StWalden StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract 17
FY17Sixth StCambridge StCharlesPaving, Sidewalk, Ped RampsStreet Reconstruction Contract FY17
FY14Smith PlFawcett StMooney StPaving, Sidewalk, Ped RampsFawcett Street
FY18Soden StWestern AveFranklin StPaving, Sidewalk, Ped RampsWestern Avenue Reconstruction Contract 2
FY13Spring StFulkerson StThird StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract 14
FY13Spring StThird StFirst StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract 14
FY15Standish StVassal LnHuron AveSewer Separation, Paving, Sidewalk, Ped RampsHuron A Sewer Separation Contract
FY15State StWindsor StOsborn StPaving, Sidewalk, Ped RampsNovartis
FY15Temple StMass AveBishop Allen DrPaving, Sidewalk, Ped RampsMiscellaneous Sidewalk Contract
FY16Thorndike StDead End Beyond FulkersonThird StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract FY15B
FY15Tremont StGardner Rd Paving, Ped RampsStreet Reconstruction Contract 17
FY14Tudor StBrookline StSidney StSewer Separation, Paving, Ped RampsCommon Manhole Removal Contract 7
FY14Tufts StMagazine StPearl StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract 16
FY13Upton StPleasant StMagazine StSidewalkMiscellaneous Sidewalk Contract
FY14Valentine StBrookline StPearl StSewer Separation, Paving, Ped RampsCommon Manhole Removal Contract 7
FY15Vassal LaneLakeview AveStandish StSewer Separation, Paving, Sidewalk, Ped RampsHuron A Sewer Separation Contract
FY16Vassal LaneStandish StHuron AveSewer Separation, Paving, Sidewalk, Ped RampsHuron B Sewer Separation Contract
FY16Walden StVassal LnConcord AveSewer Separation, Paving, Sidewalk, Ped RampsHuron B Sewer Separation Contract
FY16Walden StConcord AveGarden StSewer Separation, Paving, Sidewalk, Ped RampsConcord Avenue Sewer Separation Contract
FY18Walden StShermanGarden StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract FY18
FY13Waterhouse StMass AveGarden StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract 15
FY15Waterman RdStandish StCul De SacSewer Separation, Paving, Sidewalk, Ped RampsHuron A Sewer Separation Contract
FY14Waverly Street PathErieMirriamPaving, Sidewalk, Ped RampsWaverly Street Path
FY18Webster AveLincolk LnHampshire StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract FY18
FY15Western AveGreen StMemorial DrSewer Separation, Paving, Sidewalk, Ped RampsWestern Avenue Reconstruction Contract
FY16Williard StMt Auburn StFoster StSewer Separation, Paving, Sidewalk, Ped RampsWillaird Street Sewer Separation
FY16Windsor StMass AveState StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract FY16
FY15Windsor StMass AveMain StPaving, Sidewalk, Ped RampsNovartis
FY13Woodbridge StMass AveSomervillePaving, Sidewalk, Ped RampsStreet Reconstruction Contract 15
FY16Wyman RdSparks StCul De SacSewer Separation, Paving, Sidewalk, Ped RampsHuron B Sewer Separation Contract
   
  DPW will review on an annual basis and may revise based on changing conditions. List current as of 4/1/2013
   
 