Five Year Street and Sidewalk Reconstruction Plan
  Below is a list of streets and sidewalks that are scheduled for reconstruction between FY2015 and FY2020. To learn more about the City' s approach to prioritizing street and sidewalk reconstruction please see the full five year street and sidewalk plan (pdf).

 
YearStreetFromToScopeContract
FY19Albany St  Paving, Sidewalks, Ramps
FY18Ames StBroadwayMain StPaving, Sidewalks, Ped RampsBoston Properties
FY19Ames StMain StMemorial DrivePaving, Sidewalks, RampsMIT
FY22Amherst StAmes StWadsworth StPaving, Sidewalks, RampsMIT
FY17Appleton StHighland StBrattle StPaving, Sidewalk, Ped RampsFrost Street Sewer Separation Phase 6 Contract 3F
FY20Athens StGrant StMt Auburn StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract FY20
FY17Bay State RdNew StAlpine StSewer Separation, Paving, Sidewalk, Ped RampsConcord Avenue Sewer Separation Contract
FY21Belmont StHolworthy StTown Line Street Reconstruction Contract FY21
FY20Binney StBroadwaySixth StDeveloper
FY21Binney StCardinal Medeiros AveRailroad TracksPaving, Sidewalks, RampsPrivate Development
FY20Bishop Allen DrMain StProspect StSewer Separation, Paving, Sidewalk, Ped RampsThe Port Infrastructure Improvements Project
FY20Blackstone St  Paving, Sidewalk, Ped RampsStreet Reconstruction Contract FY20
FY20Brattle StPalmer StBennett Staving, Sidewalk, Ped RampsHarvard Square 2020
FY19Brewster StAppleton StSparks StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract 23 A
FY21BroadwayGalileo Galilei WayAmes StPaving, Sidewalks, RampsPrivate Development
FY19Cambridge StAntrim StOak StPaving, Sidewalk, Ped RampsInman Square Reconstruction Contract
FY22Carleton StDeacon StAmherst StPaving, Sidewalks, RampsMIT
FY21Centre StDana StHancock St Street Reconstruction Contract FY21
FY20Channing StMt AuburnBrattle StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract FY19
FY20Cherry StMain StHarvard StPaving, Sidewalk, Ped RampsThe Port Infrastructure Improvements Project
FY20Chestnut StSidney StPleasant StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract FY20
FY20Columbia StMass AveHarvard StPaving, Sidewalk, Ped RampsThe Port Infrastructure Improvements Project
FY17Concord AveHuron AveFresh Pond PkwySewer Separation, Paving, Sidewalk, Ped RampsConcord Avenue Sewer Separation Contract
FY19Coolidge PlMass AveEnd (includes PL6) The Port Infrastructure Improvements Project
FY19Cottage StMagazine StPearl StSewer Separation, Paving, Sidewalk, Ped RampsCambridgeport Sewer Separation Lopez / Cottage
FY20Dana StBroadwayCambridge St Street Reconstruction Contract FY20
FY19Dawes St  Paving, Sidewalks, RampsPrivate Development
FY21Deacon St  Paving, Sidewalks, RampsMIT
FY21Dock St  Paving, sidewalks, RampsMIT
FY19Dodge StWestern AveCallender StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract FY19
FY18Dudley StMass AveClifton StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract 22
FY18Dunster StMass AveMt Auburn StPaving, Sidewalks, RampsHarvard
FY19East St  Paving, Sidewalks, RampsPrivate Development
FY20Eaton StPine StCherry StSewer SeparationThe Port Infrastructure Improvements Project
FY19Eliot StBennett StJFK StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract 23 B
FY22Elm StHampshire StSomerville Street Reconstruction Contract FY22
FY17Fern StConcord AveBay State RdSewer Separation, Paving, Sidewalk, Ped RampsConcord Avenue Sewer Separation Contract
FY19Franklin StPleasantStLandsdowne StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract 23 A
FY21Gallileo WayMain StBroadwayPaving, Ped RampsStreet Reconstruction Contract FY18
FY17Garden StWalden StField StSewer Separation, Paving, Sidewalk, Ped RampsConcord Avenue Sewer Separation Contract
FY19Gore StSomerville LineO'Brien HighwayPaving, Sidewalk, Ped RampsGore St Reconstruction
FY20Gray StMartin StLinnaean StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract FY20
FY22Gray StMartin StLinnaean St Street Reconstruction Contract FY22
FY20Green StRiver StPearl St 
FY19Green StPearl StLandsdowne StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract 24
FY19Hampshire StSomerville LineInman StPaving, Sidewalk, Ped RampsInman Square Reconstruction Contract
FY17Harding StSouthCambridge StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract 21
FY20HarvardColumbiaWindsor The Port Infrastructure Improvements Project
FY22Harvard StMass AveDana St Street Reconstruction Contract FY22
FY21Haskell StRindge AveMass Ave Street Reconstruction Contract FY21
FY22Hayward StMain StAmherst StPaving, Sidewalks, RampsMIT
FY18Healey StParker StBuckingham StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract 22
FY19Highland StReservoir StSparks StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract 23 B
FY18Holyoke StMass AveMt Auburn StPaving, Sidewalks, RampsHarvard
FY17Hurlbut StLinnean StMartin StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract 20
FY19Huron AveRaymond StConcord AvePaving, Sidewalk, Ped RampsStreet Reconstruction Contract 24
FY19Huron AveFresh Pond ParkwayAberdeen AveBike and Ped Path
FY17Huron AveFresh Pond PkwyLakeview AveSewer Separation, Paving, Sidewalk, Ped RampsHuron B Sewer Separation Contract
FY17Huron AveLakeview AveConcord AveSewer Separation, Paving, Sidewalk, Ped RampsHuron B Sewer Separation Contract
FY22Jay StRiver StKinnaird StPaving, Sidewalk, Ped RampsWestern Avenue Reconstruction Contract 2
FY18Kenwood StPutnam AvePrince StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract 21
FY22Kinnaird StRiver StHancock StPaving, Sidewalk, Ped RampsWestern Avenue Reconstruction Contract 2
FY22Kirkland StOxford StSomerville LineSewer Separation, Paving, Sidewalk, Ped RampsSewer Separation Agassiz -- Kirkland
FY18Lawn StOxford StCushing StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract 21
FY17Linskey WayThird StFirst StPaving, Sidewalks, RampsPrivate Development
FY18Longfellow BridgeBostonThird StPavings, Sidewalks, RampsMassDOT
FY19Lopez StBrookline StPearl StSewer Separation, Paving, Sidewalk, Ped RampsCambridgeport Sewer Separation Lopez / Cottage
FY20Maple AveBroadwayCambridge St Street Reconstruction Contract FY20
FY20Maple AveBroadwayCambridge StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract FY20
FY17Mass AveSellers StPleasant StSidewalk, Ped Ramps South Side OnlyStreet Reconstruction Contract 19
FY17Mass AveWestern AvePearl StSidewalk, Ped Ramps South Side OnlyStreet Reconstruction Contract 19
FY19Mass AveNorfolk StDouglas StSidewalk, Ped Ramps North Side OnlyThe Port Infrastructure Improvements Project Phase 1
FY17Mass AveLinnaean StSomerville AvePaving, Ped RampsStreet Reconstruction Contract 20
FY21Montgomery StHarvey StRindge Ave Street Reconstruction Contract FY21
FY17Muller AveChurchill AveMurray Hill RdPaving, Sidewalk, Ped RampsStreet Reconstruction Contract 20
FY17Newport RdMass AveForrest StSewer Separation, Paving, Sidewalk, Ped RampsFrost Street Sewer Separation Phase 6 Contract 3F
FY22NorfolkBroadwayHampshire Street Reconstruction Contract FY22
FY19North First St  Paving, Sidewalks, RampsPrivate Development
FY19North Point BlvdCharlestown AveWater StPaving, Sidewalks, RampsPrivate Development
FY19North St  Paving, Sidewalks, RampsPrivate Development
FY19O'Brien HighwayWater StMuseum WayPaving, Sidewalk, Ped RampsNorthpoint Development
FY19Park AveHuron AveHolworthy StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract 24
FY18Parker StBuckingham StConcord AvePaving, Sidewalk, Ped RampsStreet Reconstruction Contract 22
FY18Pearl StGranite StErie StPaving, Sidewalk, Ped RampsPearl Street Reconstruction Project Contract 19
FY18Pearl StErie StMass AvePaving, Sidewalk, Ped RampsPearl Street Reconstruction Project Contract 19
FY20Pine StSchool StHarvard StPaving, Sidewalk, Ped RampsThe Port Infrastructure Improvements Project
FY18Plympton StMemorial DrMill StPaving, Sidewalks, RampsHarvard
FY17Porter StHarding StWarren StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract 21
FY17Reservoir StHighland AveVassal LnSewer Separation, Paving, Sidewalk, Ped RampsHuron B Sewer Separation Contract
FY17Richard AveMass AveMuller AvePaving, Sidewalk, Ped RampsStreet Reconstruction Contract 20
FY19Riedesel AveBrattle StBrewster StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract 23 A
FY20River StMemorial DrMass AveSewer Separation, Paving, Sidewalk, Ped RampsRiver Street Sewer Separation
FY22Roberts RdKirkland StCambridge StSewer Separation, Paving, Sidewalk, Ped RampsSewer Separation Agassiz -- Kirkland
FY17Roseland StMass AveSomerville LineSewer Separation, Paving, Sidewalk, Ped RampsFrost Street Sewer Separation Phase 6 Contract 3F
FY19Rufo RdGore StSomerville LinePaving, Sidewalks, Ped RampsGore Street Reconstruction
FY20School StBishop Allen DrWindsor StPaving, Sidewalk, Ped RampsThe Port Infrastructure Improvements Project
FY17Second StLinskey WayBinney StPaving, Sidewalks, RampsPrivate Development
FY21Shepard StGarden StMass AvePaving, Sidewalk, Ped RampsStreet Reconstruction Contract FY21
FY19Sixth StCambridge StCharlesPaving, Sidewalk, Ped RampsStreet Reconstruction Contract 23 A
FY18Sixth St Ped WalkwayBinney StBroadwaySidewalkPrivate Development
FY22Soden StWestern AveFranklin StPaving, Sidewalk, Ped RampsWestern Avenue Reconstruction Contract 2
FY19St Mary rdInman StProspect StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract 23 A
FY18Thorndike StDead End Beyond FulkersonThird StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract 21
FY22Wadsworth StMain StMemorial DrPaving, Sidewalks, RampsMIT
FY17Walden StVassal LnConcord AveSewer Separation, Paving, Sidewalk, Ped RampsHuron B Sewer Separation Contract
FY19Walden StShermanGarden StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract 24
FY20Washington StNorfolk StPortland StPaving, Sidewalk, Ped RampsThe Port Infrastructure Improvements Project
FY19Water St  Paving, Sidewalks, RampsPrivate Development
FY19Webster AveLincoln LnHampshire StPaving, Sidewalk, Ped RampsStreet Reconstruction Contract 24
FY19West Boulevard  Paving, Sidewalks, RampsPrivate Development
FY19Willard StMt Auburn StBrattle StSewer Separation, Paving, Sidewalk, Ped RampsWillard Street Sewer Separation
FY20Windsor StMain StHarvard StPaving, Sidewalk, Ped RampsThe Port Infrastructure Improvements Project
   
  DPW will review on an annual basis and may revise based on changing conditions. List current as of 3/15/2016
   
 