Cambridge Community Development Department
 city manager city council mayor's office departments paybills working calendar cityhome
 
Community Development Department header with picture of 344 Broadway Link to Cambridge home page Information about 344 Broadway, a green building Link to Community Development Department home page
Divisions & Programs Top Links

Use the Site Map to navigate
the site

Western Avenue Reconstruction

What's Happening Now

Click link to Construction starts summer 2012 and is expected to end autumn 2014.

Click link to The Final Design & Construction flyer is available.

Click link toWe expect a contractor to be on board in the spring, with construction starting this summer.  Work hours for the project will be 7:00 A. M. to 4:00 P. M..  During construction, crews will maintain at least one travel lane on Western Avenue, with occasional detours.  Every effort will be made to maintain as much parking as possible, and pedestrian, bicycle, and MBTA access will be maintained. The contractor and police details will coordinate access to neighbors’ private property if needed. 

Click link toPublic Works will hold a community meeting in the spring to introduce the contractor, present the phasing of the project, discuss construction details, and address resident questions and concerns. The underground stormwater and sewer system, water main, roadway, and sidewalks on Western Avenue will all be replaced from Green Street to Memorial Drive. NSTAR Gas will resume upgrades in the roadway early this spring.

Click link toJoin the Western Avenue email list and learn about the project and upcoming construction:

About the Project

Western Avenue is scheduled to be fully reconstructed beginning in fall, 2011. The underground stormwater and sewer system, roadway and sidewalks will all be replaced from Franklin Street to Memorial Drive. The redesign considers all street users: walkers, bicyclists, bus riders and drivers. The public process began in January 2010. Neighborhood walks and community-wide meetings have been held. An advisory committee met regularly. Following are the project goals that were developed in conjunction with the Advisory Committee:

  • Ensure corridor is safe for all users
  • Maintain adequate traffic flow
  • Reinforce residential character
  • Ensure appropriate traffic speed
  • Improve conditions for walking, bicycling and transit riders
  • Meet and exceed accessibility requirements
  • Improve access to businesses
  • Help meet stormwater environmental goals through green design
  • Provide adequate parking
  • Promote environmental sustainability
  • Improve landscaping

Return to Top

Final Design

The conceptual design for the surface was selected in the fall of 2010. The Conceptual Design is shown here. From fall 2010 until January 2012, the project has been advanced to 100% engineering design.

The final design Pleasant St. to Blackstone St. will have two vehicle travel lanes, parking on both sides, and a separated bicycle  lane (raised cycle track). Pedestrian safety will be improved with raised crosswalks on (unsignalized) sidestreets, curb extensions, and new crosswalks.  New trees, planting beds, trash/recycling containers, and energy efficient streetlights will be installed. The new design will improve pedestrian crossings at Pleasant / Western / Franklin and at Blackstone.

Cronin Park  will be enlarged, landcaped, and include seating, a  rain garden, and a permanent public art installation “Breaking Bread,” which consists of a custom designed table and fixed chairs lit by metal "baroque" inspired chandeliers. (see Public Art, below, for details). A concept plan for the park may be viewed here.

100% design drawings for the project will be posted to the website soon.

Return to Top

Public Art

We are very pleased to announce that $100,000 of the Western Avenue construction budget has been set aside to commission an artist to complete a public art project associated with Western Avenue. This is standard practice for large street rehabilitation projects.

  • The Cambridge Arts Council assembled an Art Jury to review artist portfolios. A representative of the Art Jury and the Cambridge Arts Council staff interviewed the Western Avenue Advisory Committee on June 17, 2010 to obtain community perspectives about the Western Avenue Reconstruction Project and the neighborhood in general. They brought this feedback to the Art Jury as a whole, who then narrowed down the field of potential artists. The Art Jury selected three artists as finalists: Vaughn Bell, Matthew Geller, and Matthew Mazzotta.
  • The artists were interviewed on September 2, 2010 by the Site Committee comprised of representatives from the Art Jury, Cambridge Arts Council staff, Public Art Commission, Community Development Staff, and the Western Avenue Advisory Committee,
  • Matthew Mazzotta was chosen as the artist to be commissioned for the project. He met with the Advisory Committee and also participated in public meetings to talk to neighbors while formulating his ideas for the project
  • The project, entitled Breaking Bread, may be viewed here. The location of this project within Cronin Park may be viewed here.

Return to Top

Public Input Process

Public input process for the surface redesign ran from January 2010 through June 2011 and included eight Advisory Committee meetings, five neighborhood walks , and  six public meetings.

Five concept alternatives were developed to identify the full range of potential options for Western Avenue, and extensive community feedback  was taken into consideration.  See the Community Design Process booklet, June 2010 (5.4 MB).

The following evaluation criteria was developed by city staff and the advisory committee to guide the design process:

  • Traffic calming effect/vehicle speed  reduction
  • Pedestrian crossing safety
  • Expanded sidewalk space
  • Bicycle facility safety and comfort
  • Bus operations and efficiency
  • Rush hour vehicle capacity
  • Parking availability
  • Snow clearance and street  cleaning
  • Emergency vehicle access
  • Construction cost
  • Community support

Click link toIn October 2010, a final conceptual design was selected. See the Conceptual Design Selection Booklet, October 2010. This file is in PDF format and requires use of the free Adobe Acrobat viewer.

Click link toView a PDF of some Perspective Renderings. Click on the following images to see sample drawings

Return to Top

Community Walks

These informal walks were led by city staff with occasional outside guests. The walks provided opportunities for neighbors to learn more about the project, and provide input to city staff. The walks were free and open to the public. Each walk started near Central Square, went down Western Avenue to the Charles River, and back.

Click link toView some photos of past walks.

Click link toPast Walks

  • Proposed Conceptual Design Walk: Thursday October 28, 2010, 5:30 P. M. Meet at Andala Café. Click here for map. Led by Jeff Rosenblum, Project Manager for Western Avenue surface design, Community Development Department.
  • Concepts Walk: Sunday June 27, 2010, 4:00 P. M. Meet at Andala Café. Click here for map. Led by Jeff Rosenblum, Project Manager for Western Avenue surface design, Community Development Department.
  • Project Overview Walk: Monday April 5, 2010, 6:00 P. M. to 7:30 P. M. Meet at Andala Café. Click here for map. Led by Jeff Rosenblum, Project Manager for Western Avenue surface design, Community Development Department
  • Human Centered Design Walk: Monday April 12, 2010,6:00 P. M. to 7:30 P. M. Meet at Au Bon Pain. Click here for map. Led by Chris Hart, Institute for Human Centered Design and Michael Muehe, Executive Director, Cambridge Commission for Persons with Disabilities.
  • Traffic, Signals, and Stop Signs Walk: Monday April 26, 2010, 6:00 P. M. to 7:30 P. M. Meet at Andala Café. Click here for map. Led by Jeff Parenti, City Traffic Engineer.

Return to Top

Resources

These files are in PDF format and require use of the free Adobe Acrobat viewer.

Return to Top

For More Information

For more information about the Western Avenue Reconstruction project call Jeff Rosenblum, jrosenblum@cambridgema.gov, at 617/349-4615. The Community Development Department TTY line is 617/349-4621.

Click link toSign up to receive updates by email or postal mail.

Return to Top

 

Click link toReturn to Roadway, Sidewalk and Path Projects

Click link toReturn to Environmental and Transportation Planning Division

Click link toReturn to Community Development Department Home

 

© 2004 - 2010 Community Development Department, City of Cambridge, Massachusetts

City Home  |   search   |   publications   |   working   |   contact us  |   directions  |   disclaimer   |   privacy   |   CDD Home